WP1 Management and Coordination
Duration: M1 – M36 |
|
Objectives
|
To coordinate the project work towards the achievement of the objectives within the proposed scope and financial resources based on smooth co-operation between the partners. |
Deliverables
|
D1.1 – Quality and Risk Contingency Plan [M3]
D1.2 – Annual Progress Reports [M12, M24, M36]
D1.3 – Final Project Report [M36] |
WP2 Validation requirements and data holdings
Duration: M1 – M7 |
|
Objectives
|
The main objective of this WP is to ensure the access to the required data and to provide all the necessary specifications for successful testing of the project’s hypothesis. |
Deliverables
|
D2.1 – Pilot requirements and validation criteria [M4]
D2.2 – Data access specification [M6]
D2.3 – System architecture design [M6]
D2.4 – PLACE core server platform [M7] |
WP3 Geospatial context modelling
Duration: M6 – M32 |
|
Objectives
|
This WP shall focus on the research of information extraction algorithms and their chaining, with the objective to develop a structured context representation extracted from heterogeneous geospatial sensory data. |
Deliverables
|
D3.1 – Feature extraction library [M12]
D3.2 – Feature selection algorithm [M18]
D3.3 – Algorithm for general context establishment and representation [M24] |
WP4 Advanced geospatial predictive analytics
Duration: M12 – M32 |
|
Objectives
|
The main objective of this WP is to develop new methods for geospatial predictive analytics, capable of capitalising on the structured representation of context. |
Deliverables
|
D4.1 – Context enrichment services [M28]
D4.2 – Geospatial regression models [M30]
D4.3 – Environmental simulation services [M30]
D4.4 – Visual analytics services [M32] |
WP5 Component integration and hypothesis testing
Duration: M24 – M36 |
|
Objectives
|
The core objectives of this WP are:
- To implement pilot demonstration and, thus, proving TRL 4, and
- To elaborate on a road map towards its sustainable implementation after the end of the project.
|
Deliverables
|
D5.1 Operational system, deployed on testing infrastructure [M32]
D5.2 Operational Performance Verification Report [M34]
D5.3 Service Utility Assessment and Road Map [M36] |
WP6 Dissemination and exploitation
Duration: M1 – M36 |
|
Objectives
|
This WP is intended to promote the project outcomes in order to create the conditions necessary for a wider uptake and replication of the project outcomes by the scientific community, as well as the industry and end-users.
|
Deliverables
|
D6.1 Dissemination and Replication Strategy [M3]
D6.2 Newsletter [one month before each event/milestone – M5, M22, M31, M35]
D6.3 Demonstration facilities [M6, M12, M18, M24, M30, M36] |
|
WP1 |
WP2 |
|
|
|
WP6 |
P h a s e 1
|
1 |
|
|
|
|
|
|
2 |
|
|
|
|
|
|
3 |
|
|
|
|
|
|
4 |
|
|
|
|
|
|
5 |
MS1 |
|
|
WP3 |
|
|
|
P h a s e 2
|
6 |
|
|
|
|
|
|
7 |
|
|
|
|
|
|
8 |
|
|
|
|
|
|
9 |
|
|
|
|
|
|
10 |
|
|
|
|
|
|
11 |
|
|
|
WP4 |
|
|
12 |
|
|
|
|
|
|
13 |
|
|
|
|
|
|
14 |
|
|
|
|
|
|
15 |
|
|
|
|
|
|
16 |
|
|
|
|
|
|
17 |
|
|
|
|
|
|
18 |
|
|
|
|
|
|
19 |
|
|
|
|
|
|
20 |
|
|
|
|
|
|
21 |
|
|
|
|
|
|
22 |
|
|
|
|
|
|
23 |
MS2 |
|
|
|
|
WP5 |
|
24 |
|
|
|
|
|
|
25 |
|
|
|
|
|
|
26 |
|
|
|
|
|
|
27 |
|
|
|
|
|
|
28 |
|
|
|
|
|
|
29 |
|
|
|
|
|
|
30 |
|
|
|
|
|
|
31 |
|
|
|
|
|
|
32 |
MS3 |
|
|
|
|
|
|
P h a s e 3
|
33 |
|
|
|
|
|
|
34 |
|
|
|
|
|
|
35 |
|
|
|
|
|
|
36 |
|